May 2026
The Library Board of Trustees authorized the Fiscal Officer to enter into an agreement for landscape architect services with Behnke Associates.
Bialosky Cleveland and Turner Construction teams worked to complete items from the punch list.
The Library's Donor Wall, recognizing donations from library supporters, was installed by Arreya Digital Signage.
April 2026
The last day for library service provided out of the East 185th Street location was Friday, April 3.
Armbruster Moving & Storage completed packing library books and transferring materials and furniture from EPL at 185th to Main Library.
New furniture for public and staff spaces was delivered.
March 2026
Turner Construction began installing cabinetry, carpeting, painting and working on finishes.
The library staff began preparing for the upcoming move back to main library by packing offices and work spaces.
Director Armstrong hosted the first Renovation Town Hall of 2026 to share updates on the library's renovation project.
February 2026
Euclid Public Library posted a landscaping RFQ on the library website to solicit qualified contractors to design, install and maintain the landscaping and irrigation system at the renovated library.
The Library Board of Trustees approved the closure of Euclid Public Library at the East 185th location from April 3-May 31, 2026, to accommodate for the completion of the renovation and the return to the Main Library site at 631 East 222nd Street.
Turner Construction installed interior lights, ceramic tile and millwork.
January 2026
The Library Board of Trustees approved the Visual Identity Guidelines created by Frozen Creative under the direction of Euclid Public Library's Marketing Manager, Courtney Barnes.
Turner construction began installing drywall and finishes.